Do I need a Notice of Commencement?
A Notice of Commencement is required if the value of work exceeds $2,500.

The Notice of Commencement must be recorded with Lake County’s recording office and then filed with the City of Mount Dora Building and Fire Prevention Services before the first inspection will be scheduled.

Lake County Recording Office
122 E. Main St.
Tavares, FL 32778

City of Mount Dora Building and Fire Prevention Services
510 N. Baker St.
Mount Dora, FL 32757

Exception: If there is a permit being pulled for mechanical change-out only and it is less than $7,500, then a Notice of commencement is not required.